Key Takeaway
Fells Reservoir Dam - #3 is classified as significant hazard in Massachusetts. It was completed in 1898 and is 128 years old. Its primary use is water supply. Significant hazard means failure could cause economic or environmental damage. Learn more.
Physical Details
| Dam Height | 25 ft (taller than 79.2% in MA) |
| Dam Length | 130 ft |
| Dam Type | Earth |
| Max Storage | 150 acre-ft |
| Normal Storage | 85 acre-ft |
| Surface Area | 14 acres |
| Drainage Area | 0 sq mi |
| Year Completed | 1898 (128 years old) |
| NID ID | MA03306 |
Safety Information
No probable loss of human life, but can cause economic loss, environmental damage, or disruption of lifeline facilities.
Hazard potential describes downstream consequences of failure, not the dam's current condition. What does this mean?
Ownership
DCR - DEPT. OF CONSERVATION & RECREATION
State Government
Nearby Dams
Fells Reservoir Dam - #2
Middlesex, MA
Significant Hazard 12 ftFells Reservoir Dam - #6
Middlesex, MA
Significant Hazard 17 ftFells Reservoir Dam - #8
Middlesex, MA
High Hazard 48 ftSpot Pond Dam
Middlesex, MA
Significant Hazard 18 ftSpot Pond Dike #4
Middlesex, MA
Significant Hazard 9 ftSpot Pond Dike #5
Middlesex, MA
Significant Hazard 9 ftWrights Pond Dam
Middlesex, MA
High Hazard 27 ftSouth Reservoir East Dike
Middlesex, MA
High Hazard 15 ftFrequently Asked Questions
What is the hazard classification of Fells Reservoir Dam - #3?
Fells Reservoir Dam - #3 is classified as Significant Hazard. No probable loss of human life, but can cause economic loss, environmental damage, or disruption of lifeline facilities. This classification refers to the potential downstream consequences of a failure, not the dam's current structural condition.
Who owns and operates Fells Reservoir Dam - #3?
Fells Reservoir Dam - #3 is owned by DCR - DEPT. OF CONSERVATION & RECREATION (State Government). The owner is responsible for maintenance, inspections, and compliance with dam safety regulations.
When was Fells Reservoir Dam - #3 built?
Fells Reservoir Dam - #3 was completed in 1898, making it 128 years old. Many U.S. dams were built between the 1930s and 1970s during a period of major infrastructure investment.
What is the primary purpose of Fells Reservoir Dam - #3?
Fells Reservoir Dam - #3 serves the following purposes: Water Supply. Many dams in the U.S. are multi-purpose, supporting flood control, water supply, recreation, and other uses.
How tall is Fells Reservoir Dam - #3?
Fells Reservoir Dam - #3 has a dam height of 25 ft. Dam height is measured from the natural streambed at the downstream toe to the top of the dam, and may differ from the visible height.
When was Fells Reservoir Dam - #3 last inspected?
Fells Reservoir Dam - #3 was last inspected on September 23, 2016. Inspection dates indicate when a formal review occurred, not the results of that inspection.