Key Takeaway
Davis County -Barton Creek Db is classified as high hazard in Utah. It was completed in 1984 and is 42 years old. Its primary use is flood risk reduction. High hazard means loss of life is likely if the dam fails — it does not indicate the dam's current condition. Learn more.
Physical Details
| Dam Length | 460 ft |
| Dam Type | Earth |
| Max Storage | 185 acre-ft |
| Normal Storage | 150 acre-ft |
| Drainage Area | 5 sq mi |
| Max Discharge | 600 cfs |
| Year Completed | 1984 (42 years old) |
| NID ID | UT00152 |
Safety Information
Loss of human life is likely if the dam fails.
Hazard potential describes downstream consequences of failure, not the dam's current condition. What does this mean?
Ownership
DAVIS COUNTY FLOOD CONTROL
Local Government
Nearby Dams
Weber Basin Equalizing Reservoir 18 Upper
Davis, UT
High HazardWeber Basin Equalizing Reservoir 18 Lower
Davis, UT
High HazardDavis County -Stone Creek Db
Davis, UT
High HazardDavis County - Millcreek Db #3
Davis, UT
Significant HazardWeber Basin Equalizing Reservoir 17.8
Davis, UT
High HazardWeber Basin Equalizing Reservoir 18.5
Davis, UT
High HazardBountiful City Eagle Ridge
Davis, UT
Significant HazardWeber Basin Equalizing Reservoir 17.2
Davis, UT
High HazardFrequently Asked Questions
What is the hazard classification of Davis County -Barton Creek Db?
Davis County -Barton Creek Db is classified as High Hazard. Loss of human life is likely if the dam fails. This classification refers to the potential downstream consequences of a failure, not the dam's current structural condition.
Who owns and operates Davis County -Barton Creek Db?
Davis County -Barton Creek Db is owned by DAVIS COUNTY FLOOD CONTROL (Local Government). The owner is responsible for maintenance, inspections, and compliance with dam safety regulations.
When was Davis County -Barton Creek Db built?
Davis County -Barton Creek Db was completed in 1984, making it 42 years old. Many U.S. dams were built between the 1930s and 1970s during a period of major infrastructure investment.
What is the primary purpose of Davis County -Barton Creek Db?
Davis County -Barton Creek Db serves the following purposes: Flood Risk Reduction. Many dams in the U.S. are multi-purpose, supporting flood control, water supply, recreation, and other uses.
When was Davis County -Barton Creek Db last inspected?
Davis County -Barton Creek Db was last inspected on August 29, 2023. Inspection dates indicate when a formal review occurred, not the results of that inspection.