David Peeler Dam is classified as significant hazard in Missouri. It was completed in 1999 and is 27 years old. Significant hazard means failure could cause economic or environmental damage. Learn more.
Physical Details
| Dam Height | 47 ft (taller than 93.7% in MO) |
| Dam Length | 160 ft |
| Dam Type | Earth |
| Max Storage | 8 acre-ft |
| Normal Storage | 7 acre-ft |
| Surface Area | 0 acres |
| Drainage Area | 0 sq mi |
| Year Completed | 1999 (27 years old) |
| Year Modified | 1999 |
| NID ID | MO12415 |
Safety Information
No probable loss of human life, but can cause economic loss, environmental damage, or disruption of lifeline facilities.
Hazard potential describes downstream consequences of failure, not the dam's current condition. What does this mean?
Ownership
Private
Nearby Dams
Mechlin
Howard, MO
Low Hazard 33 ftRolfling Lake Dam-Sec 36 (Dry)
Cooper, MO
High Hazard 25 ftRolfling Lake Dam Sec 6
Cooper, MO
Low Hazard 29 ftReservoir Dam
Howard, MO
High Hazard 23 ftNew Horticulture Farm Dam
Howard, MO
High Hazard 26 ftLippold Lake Dam
Howard, MO
Low Hazard 21 ftSmith Lake Dam
Cooper, MO
Low Hazard 30 ftDavis Lake Dam
Howard, MO
Low Hazard 25 ftFrequently Asked Questions
What is the hazard classification of David Peeler Dam?
David Peeler Dam is classified as Significant Hazard. No probable loss of human life, but can cause economic loss, environmental damage, or disruption of lifeline facilities. This classification refers to the potential downstream consequences of a failure, not the dam's current structural condition.
Who owns and operates David Peeler Dam?
David Peeler Dam is owned by information not available (Private). The owner is responsible for maintenance, inspections, and compliance with dam safety regulations.
When was David Peeler Dam built?
David Peeler Dam was completed in 1999, making it 27 years old. Many U.S. dams were built between the 1930s and 1970s during a period of major infrastructure investment.
How tall is David Peeler Dam?
David Peeler Dam has a dam height of 47 ft. Dam height is measured from the natural streambed at the downstream toe to the top of the dam, and may differ from the visible height.
When was David Peeler Dam last inspected?
David Peeler Dam was last inspected on November 2, 2021. Inspection dates indicate when a formal review occurred, not the results of that inspection.