Clear Springs Cs-1
Key Takeaway
Clear Springs Cs-1 is classified as significant hazard in Florida. It was completed in 1950 and is 76 years old. Its primary use is tailings. Significant hazard means failure could cause economic or environmental damage. Learn more.
Physical Details
| Dam Height | 18 ft (taller than 43.2% in FL) |
| Dam Length | 6,800 ft |
| Dam Type | Earth |
| Max Storage | 1.0K acre-ft |
| Normal Storage | 1.0K acre-ft |
| Surface Area | 56 acres |
| Drainage Area | 0 sq mi |
| Max Discharge | 0 cfs |
| Year Completed | 1950 (76 years old) |
| NID ID | FL00651 |
Safety Information
No probable loss of human life, but can cause economic loss, environmental damage, or disruption of lifeline facilities.
Hazard potential describes downstream consequences of failure, not the dam's current condition. What does this mean?
Ownership
THE MOSAIC COMPANY
Private
Nearby Dams
Clear Springs Cs-6c
Polk, FL
Significant Hazard 20 ftClear Springs Cs-6a
Polk, FL
Significant Hazard 17 ftClear Springs Marina
Polk, FL
Significant Hazard 18 ftClear Springs Cs-3
Polk, FL
Significant Hazard 18 ftClear Springs Cs-5
Polk, FL
Significant Hazard 19 ftClear Springs Cs-4
Polk, FL
Significant Hazard 27 ftPol39
Polk, FL
Unknown 45 ftPol38
Polk, FL
Unknown 9 ftFrequently Asked Questions
What is the hazard classification of Clear Springs Cs-1?
Clear Springs Cs-1 is classified as Significant Hazard. No probable loss of human life, but can cause economic loss, environmental damage, or disruption of lifeline facilities. This classification refers to the potential downstream consequences of a failure, not the dam's current structural condition.
Who owns and operates Clear Springs Cs-1?
Clear Springs Cs-1 is owned by THE MOSAIC COMPANY (Private). The owner is responsible for maintenance, inspections, and compliance with dam safety regulations.
When was Clear Springs Cs-1 built?
Clear Springs Cs-1 was completed in 1950, making it 76 years old. Many U.S. dams were built between the 1930s and 1970s during a period of major infrastructure investment.
What is the primary purpose of Clear Springs Cs-1?
Clear Springs Cs-1 serves the following purposes: Tailings. Many dams in the U.S. are multi-purpose, supporting flood control, water supply, recreation, and other uses.
How tall is Clear Springs Cs-1?
Clear Springs Cs-1 has a dam height of 18 ft. Dam height is measured from the natural streambed at the downstream toe to the top of the dam, and may differ from the visible height.