Buck Basin #2 To Basin #3 Dam
Key Takeaway
Buck Basin #2 To Basin #3 Dam is classified as high hazard in North Carolina. It was completed in 1979 and is 47 years old. Its primary use is tailings. High hazard means loss of life is likely if the dam fails — it does not indicate the dam's current condition. Learn more.
Physical Details
| Dam Length | 130 ft |
| Dam Type | Earth |
| Max Storage | 1.2K acre-ft |
| Normal Storage | 135 acre-ft |
| Surface Area | 46 acres |
| Drainage Area | 154 sq mi |
| Max Discharge | 0 cfs |
| Year Completed | 1979 (47 years old) |
| NID ID | NC05968 |
Safety Information
Loss of human life is likely if the dam fails.
Hazard potential describes downstream consequences of failure, not the dam's current condition. What does this mean?
Ownership
Duke Energy Corporation
Public Utility
Nearby Dams
Buck Ash Basin Divider Dam
Rowan, NC
High HazardBuck Main Ash Basin Dam
Rowan, NC
High HazardBuck Basin #1 To Basin #2 Dam
Rowan, NC
High HazardBuck Retention Basin Dam
Rowan, NC
Significant HazardBuck Ash Basin #1 Dam
Rowan, NC
High HazardMessinger Lake Dam
Rowan, NC
Low HazardColtrane Lake Dam
Davidson, NC
Low HazardNicholas Lake Dam
Rowan, NC
Low HazardFrequently Asked Questions
What is the hazard classification of Buck Basin #2 To Basin #3 Dam?
Buck Basin #2 To Basin #3 Dam is classified as High Hazard. Loss of human life is likely if the dam fails. This classification refers to the potential downstream consequences of a failure, not the dam's current structural condition.
Who owns and operates Buck Basin #2 To Basin #3 Dam?
Buck Basin #2 To Basin #3 Dam is owned by Duke Energy Corporation (Public Utility). The owner is responsible for maintenance, inspections, and compliance with dam safety regulations.
When was Buck Basin #2 To Basin #3 Dam built?
Buck Basin #2 To Basin #3 Dam was completed in 1979, making it 47 years old. Many U.S. dams were built between the 1930s and 1970s during a period of major infrastructure investment.
What is the primary purpose of Buck Basin #2 To Basin #3 Dam?
Buck Basin #2 To Basin #3 Dam serves the following purposes: Tailings. Many dams in the U.S. are multi-purpose, supporting flood control, water supply, recreation, and other uses.
When was Buck Basin #2 To Basin #3 Dam last inspected?
Buck Basin #2 To Basin #3 Dam was last inspected on August 24, 2022. Inspection dates indicate when a formal review occurred, not the results of that inspection.