Brogden Bridge

LAKE TSALA APOPKA· Citrus, Florida· Built 1972· Other· 7 ft tall
Low Hazard Flood Risk Reduction State Government

Key Takeaway

Brogden Bridge is classified as low hazard in Florida. It was completed in 1972 and is 54 years old. Its primary use is flood risk reduction.

Physical Details

Dam Height 7 ft (taller than 3.4% in FL)
Dam Length130 ft
Dam TypeOther
Max Storage3.0K acre-ft
Normal Storage29.7K acre-ft
Surface Area4,950 acres
Drainage Area0 sq mi
Max Discharge120 cfs
Year Completed1972 (54 years old)
NID IDFL18001

Safety Information

Low Hazard

No probable loss of human life and low economic/environmental losses expected.

Hazard potential describes downstream consequences of failure, not the dam's current condition. What does this mean?

Emergency Action Plan: No
Last Inspection: April 13, 2023
State Regulated: Yes
Regulatory Agency: SWFWMD

Ownership

SWFWMD

State Government

Nearby Dams

Frequently Asked Questions

What is the hazard classification of Brogden Bridge?

Brogden Bridge is classified as Low Hazard. No probable loss of human life and low economic/environmental losses expected. This classification refers to the potential downstream consequences of a failure, not the dam's current structural condition.

Who owns and operates Brogden Bridge?

Brogden Bridge is owned by SWFWMD (State Government). The owner is responsible for maintenance, inspections, and compliance with dam safety regulations.

When was Brogden Bridge built?

Brogden Bridge was completed in 1972, making it 54 years old. Many U.S. dams were built between the 1930s and 1970s during a period of major infrastructure investment.

What is the primary purpose of Brogden Bridge?

Brogden Bridge serves the following purposes: Flood Risk Reduction. Many dams in the U.S. are multi-purpose, supporting flood control, water supply, recreation, and other uses.

How tall is Brogden Bridge?

Brogden Bridge has a dam height of 7 ft. Dam height is measured from the natural streambed at the downstream toe to the top of the dam, and may differ from the visible height.

When was Brogden Bridge last inspected?

Brogden Bridge was last inspected on April 13, 2023. Inspection dates indicate when a formal review occurred, not the results of that inspection.

Data from the National Inventory of Dams (NID) maintained by the US Army Corps of Engineers. Dam conditions may have changed since the last update. This site is not affiliated with USACE. Do not use for emergency planning — contact your local dam safety program.