Bound Brook Dam
Key Takeaway
Bound Brook Dam is classified as significant hazard in Massachusetts. It was completed in 1999 and is 27 years old. Its primary use is water supply. Significant hazard means failure could cause economic or environmental damage. Learn more.
Physical Details
| Dam Height | 11 ft (taller than 25.5% in MA) |
| Dam Length | 200 ft |
| Dam Type | Earth |
| Max Storage | 600 acre-ft |
| Normal Storage | 324 acre-ft |
| Surface Area | 0 acres |
| Drainage Area | 9 sq mi |
| Year Completed | 1999 (27 years old) |
| NID ID | MA03197 |
Safety Information
No probable loss of human life, but can cause economic loss, environmental damage, or disruption of lifeline facilities.
Hazard potential describes downstream consequences of failure, not the dam's current condition. What does this mean?
Ownership
TOWN OF COHASSET, BOARD OF SELECTMEN
Local Government
Nearby Dams
Aaron River Dam
Norfolk, MA
High Hazard 30 ftBound Brook Pond Dam
Plymouth, MA
Low Hazard 7 ftNichols Road Dam
Norfolk, MA
Significant Hazard 10 ftStraits Pond Dam
Norfolk, MA
Significant Hazard 12 ftTriphammer Pond Dam
Plymouth, MA
Low Hazard 5 ftWoodpecker Pond Dam
Plymouth, MA
Low Hazard 7 ftFirst Herring Brook Reservoir Dam
Plymouth, MA
High Hazard 22 ftFulling Mill Pond Dam
Plymouth, MA
Significant Hazard 8 ftFrequently Asked Questions
What is the hazard classification of Bound Brook Dam?
Bound Brook Dam is classified as Significant Hazard. No probable loss of human life, but can cause economic loss, environmental damage, or disruption of lifeline facilities. This classification refers to the potential downstream consequences of a failure, not the dam's current structural condition.
Who owns and operates Bound Brook Dam?
Bound Brook Dam is owned by TOWN OF COHASSET, BOARD OF SELECTMEN (Local Government). The owner is responsible for maintenance, inspections, and compliance with dam safety regulations.
When was Bound Brook Dam built?
Bound Brook Dam was completed in 1999, making it 27 years old. Many U.S. dams were built between the 1930s and 1970s during a period of major infrastructure investment.
What is the primary purpose of Bound Brook Dam?
Bound Brook Dam serves the following purposes: Water Supply. Many dams in the U.S. are multi-purpose, supporting flood control, water supply, recreation, and other uses.
How tall is Bound Brook Dam?
Bound Brook Dam has a dam height of 11 ft. Dam height is measured from the natural streambed at the downstream toe to the top of the dam, and may differ from the visible height.
When was Bound Brook Dam last inspected?
Bound Brook Dam was last inspected on July 21, 2011. Inspection dates indicate when a formal review occurred, not the results of that inspection.